Everything for the UK and Europe →A day-by-day-to-week-by-week view of the last ninety days before go-live: what is frozen, what is rehearsed and who decides.
Cutover is a rehearsed event, not a weekend of improvisation. In the last ninety days the questions are always the same: is the data right, is the plan timed, and who calls go or no-go.
YesProceed to the rehearsal.
NoStop. Fix the mapping.
YesConfirm the window.
NoReduce scope, add resource or move the date.
YesGo.
NoHold. Training and acceptance are gates, not courtesies.
The cutover window depends on data volumes and entities, which is why rehearsals are timed. The preparation runs over the last ninety days.
The steering committee, on written evidence from the reconciliation, rehearsals, testing and support readiness.
It starts with a 45-minute consultation, then a discovery and fit-gap workshop on your own processes. You receive a written fit-gap and a phased plan before a programme is agreed. Four phases follow, each with something you can use and review.
Process workshops, data audit, and a fit-gap against the standard product.
Solution blueprint, integration map, and the extensions we will actually need.
Configuration, migration rehearsal, role-based training, UAT and phased cutover.
Hypercare, managed services, client portal, scheduled optimisation reviews.
What drives the cost: users, legal entities and currencies, integrations, data migration and the gaps found against standard. See how pricing works, run the three-minute readiness score, or book a consultation.